Bertha is biggest obstacle to finishing Seattle tunnel

Apr 8, 2015, 1:06 PM | Updated: 2:45 pm

Bertha has only completed about a 10th of the Seattle tunnel project. (WSDOT flickr)...

Bertha has only completed about a 10th of the Seattle tunnel project. (WSDOT flickr)

(WSDOT flickr)

The most significant risk to the Alaskan Way Viaduct replacement project is the function of the tunnel boring machine itself, according to a new report by an expert review panel.

As of March 3, 2015, Bertha has traveled 1,083 of 9,270 feet. Crews are working to repair a broken cutter head after moving the machine into an access pit.

The report goes on to say that “this will remain as the single most significant project risk until the tunnel boring machine breaks through at the north end of the tunnel alignment.”

The good news is the panel predicts that despite Bertha’s breakdown, taxpayers might not be on the hook for extra money.

“It’s an underground project so it’s very common to have differing site conditions that occur in underground projects. The state had the foresight to understand that, know that and have the mechanisms within the contract to deal with those,” panel chair Dr. Patricia Galloway told KIRO Radio.

Galloway said a worst-case prediction shows Bertha’s breakdown will cost the state $317.5 million. The panel identified $329 million to cover those costs, including money from a contingency fund, an insurance policy on Bertha, and savings from other parts of the tunnel finished early.

The study also pointed out that little progress has been made to secure tolling revenues for the project.

“Delayed decision making on tolling matters creates the risk that future decision makers may have reduced willingness to authorize tolling,” the report said.

Without tolling, there isn’t enough funding to complete post-tunnel projects, the most costly of which is the new Alaskan Way surface street.

Despite the report, not everyone is convinced the tunnel will be completed.

Please follow our Community Guidelines

MyNorthwest News

9th ave...

Chris Sullivan

SDOT plans to paint over Convention Center street art that won’t come off 9th Ave.

SDOT, which granted the Seattle Convention Center the permit to paint 9th Ave., now has a plan to fix the problem.

7 hours ago

Oreogate...

Katrina Guischard

‘Oreogate’ has parents picking sides over a kindergartner’s lunchbox

A chocolate sandwich cookie has become the center of a viral parenting showdown, real or not, dubbed "Oreogate."

8 hours ago

I-405 (2)...

Nate Connors

A full closure of I-405 will make for a rough weekend commute

The Washington State Department of Transportation (WSDOT) has scheduled a full closure of northbound I-405 between Renton and Bellevue.

8 hours ago

shooting...

MyNorthwest Staff

Woman in custody after domestic violence incident leads to officer-involved shooting in Seattle

A woman is in custody after a domestic violence incident turned into an officer-involved shooting in Seattle.

12 hours ago

planend parenthood...

Julia Dallas

Man arrested for allegedly trying to light Bellevue Planned Parenthood on fire

A 36-year-old man was arrested for allegedly trying to set a Bellevue Planned Parenthood on fire based on his own personal beliefs.

13 hours ago

Krista Perez candidate DUI...

Frank Lenzi

WA house candidate Krista Perez pleads not guilty to DUI in Tacoma court

Washington state House candidate Krista Perez, charged with DUI after a five-vehicle crash in Tacoma, appeared in Tacoma Municipal Court Friday and pleaded not guilty.

13 hours ago

Bertha is biggest obstacle to finishing Seattle tunnel