Bertha is biggest obstacle to finishing Seattle tunnel

Apr 8, 2015, 1:06 PM | Updated: 2:45 pm

Bertha has only completed about a 10th of the Seattle tunnel project. (WSDOT flickr)...

Bertha has only completed about a 10th of the Seattle tunnel project. (WSDOT flickr)

(WSDOT flickr)

The most significant risk to the Alaskan Way Viaduct replacement project is the function of the tunnel boring machine itself, according to a new report by an expert review panel.

As of March 3, 2015, Bertha has traveled 1,083 of 9,270 feet. Crews are working to repair a broken cutter head after moving the machine into an access pit.

The report goes on to say that “this will remain as the single most significant project risk until the tunnel boring machine breaks through at the north end of the tunnel alignment.”

The good news is the panel predicts that despite Bertha’s breakdown, taxpayers might not be on the hook for extra money.

“It’s an underground project so it’s very common to have differing site conditions that occur in underground projects. The state had the foresight to understand that, know that and have the mechanisms within the contract to deal with those,” panel chair Dr. Patricia Galloway told KIRO Radio.

Galloway said a worst-case prediction shows Bertha’s breakdown will cost the state $317.5 million. The panel identified $329 million to cover those costs, including money from a contingency fund, an insurance policy on Bertha, and savings from other parts of the tunnel finished early.

The study also pointed out that little progress has been made to secure tolling revenues for the project.

“Delayed decision making on tolling matters creates the risk that future decision makers may have reduced willingness to authorize tolling,” the report said.

Without tolling, there isn’t enough funding to complete post-tunnel projects, the most costly of which is the new Alaskan Way surface street.

Despite the report, not everyone is convinced the tunnel will be completed.

Please follow our Community Guidelines

MyNorthwest News

power outage...

MyNorthwest Staff

Power restored in Capitol Hill

Power has been restored in Seattle's Capitol Hill neighborhood.

3 hours ago

ferry terminal repairs orcas island...

MyNorthwest Staff

Orcas Island ferry terminal repairs could take 2 weeks as large vehicles remain restricted

Repairs to the Orcas Island ferry terminal’s transfer span could take up to two weeks after engineers found cracks in two supporting steel beams.

4 hours ago

Wilson (1)...

James Lynch

Seattle council to vote on overriding Wilson’s RV permit veto Thursday

A showdown is brewing between Seattle Mayor Katie Wilson and the Seattle City Council over RV parking.

5 hours ago

Otter Bar...

Paola Tristan Arruda, KIRO 7 News

Otter Bar to close after seven years as Eastlake construction, rising costs take toll

After seven years in Seattle’s Eastlake neighborhood, Otter Bar is preparing to close its doors for good.

6 hours ago

Sound Transit light rail car stuck...

Frank Lenzi

Car gets stuck near Rainier Beach station in Seattle’s second light rail track incident this year

For the second time this year, a car got stuck on Seattle light rail tracks.

6 hours ago

seattle drug trafficking ghost gun...

MyNorthwest Staff

Seattle man sentenced to 5 years for drug trafficking while armed with ‘ghost gun’

A 24-year-old Seattle man was sentenced Friday to five years in prison for dealing cocaine while armed with a 9mm polymer gun with an extended magazine.

7 hours ago

Bertha is biggest obstacle to finishing Seattle tunnel