MYNORTHWEST NEWS

Bertha makes it through concrete wall into access pit

Feb 19, 2015, 10:35 AM | Updated: 5:09 pm

Bertha the drill has broken through the 20-foot wall of concrete on the Seattle waterfront. (WSDOT ...

Bertha the drill has broken through the 20-foot wall of concrete on the Seattle waterfront. (WSDOT photo)

(WSDOT photo)

After sitting idle for more than a year, Bertha the drill broke through a 20-foot wall of concrete on the Seattle waterfront Thursday afternoon.

The world’s largest tunneling machine will go two more feet before stopping to build another concrete tunnel ring.

The Washington State Department of Transportation said Bertha will continue to move forward in 6 and a half foot increments, stopping to build concrete rings on its way into the pit.

Once Bertha’s front end is entirely exposed in the pit, crews will begin the dismantling process.

“STP has told us that taking the machine apart and lifting it to the surface will take significant time and effort,” said WSDOT.

Once the disassembling process is complete, a massive crane will lift the front of the machine to the surface for repairs and improvements.

“We’ve got seals, that are rubber seals that prevent metal to metal contact between the rotating piece and the fixed piece,” explained Chris Dixon, project manager with Seattle Tunnel Partners. “We filled that with grease. Those seals became damaged and that’s what we’re replacing.”

WSDOT said workers and manufacturer Hitachi Zosen will continue to monitor Bertha to make sure it doesn’t overheat.

The tunnel, which will run about 2 miles under the city, is designed to replace the Alaskan Way viaduct, damaged in a 2001 earthquake. The project is two years behind schedule.

If all goes as planned, the tunnel is expected to open to traffic at the end of 2017.

Create your own user feedback survey

So what’s next? Seattle Tunnel Partners released a repair plan via video in June:

Please follow our Community Guidelines

MyNorthwest News

Hood Canal Bridge (1)...

MyNorthwest Staff

Stalled semitruck cleared after blocking Hood Canal Bridge for more than an hour

A stalled semitruck was blocking the entrance to the Hood Canal Bridge.

4 hours ago

celestial events...

Julia Dallas

4 celestial events will light up the sky on Aug. 12

Wherever you are on Wednesday, Aug. 12, take a moment to look up. Four celestial events will be taking place throughout the day.

5 hours ago

seattle man arrest...

James Lynch

Online sting leads to arrest of Seattle man as law enforcement ramps up predator crackdown

The Kitsap County Sheriff’s Office (KCSO) said an online undercover operation has led to the arrest of a 29-year-old Seattle man.

6 hours ago

_Aaron Farinacci spokane fires old trails fire...

MyNorthwest Staff

$2M bail set after arson suspect admits to planning Old Trails Fire, setting 25 other fires since July 2025

The man arrested for arson in connection with the Old Trails Fire in Spokane told detectives he planned to start the fire.

7 hours ago

Kitchen & Market...

Julia Dallas

Kitchen & Market expanding to Seattle neighborhood in 2027

Kitchen & Market, which touts itself as being "way more than a grocery store," is expanding in Seattle.

8 hours ago

Spokane fires (1)...

Brooke Griffin, KIRO 7 News

Spokane community helping each other and emergency responders during devastation

As three wildfires continue to burn across Spokane County Thursday morning, the community is coming together to help first responders.

8 hours ago

Bertha makes it through concrete wall into access pit