Bertha not expected to resume digging Seattle tunnel until late March 2015

Apr 21, 2014, 1:16 PM | Updated: 5:18 pm

Officials say it will be nearly a year before the damaged tunnel-boring machine stuck under downtown Seattle can start digging again.

The Washington State Department of Transportation has released a new schedule provided by Seattle Tunnel Partners indicating digging is expected to resume on the SR-99 Seattle tunnel project by the end of March 2015.

The new timeline from STP outlines all the steps they are undertaking to get Bertha back on track, including the excavation to reach the machine and the time they anticipate it will take to complete repairs.

According to the new timeline, they will begin building walls of the underground access pit in late May, followed by excavation of the pit July through September.

The next phase, beginning in October, involves making the actual repairs to the machine. STP plans to remove the cutterhead and replace the main bearing and add a more robust seal system.

Chris Dixon, the project manager for Seattle Tunnel Partners, says the repairs pose a significant engineering challenge and have to be done safely.

By February, they expect to be able to conduct tests on the machine to get her back digging by late March.

Bertha has been stalled since late December. The machine is only one-tenth of the way toward completing the 1.7-mile tunnel. The new timeline delays tunnel boring by up to 16 months, but STP tells WSDOT they hope to recover four months to meet the November 2016 tunnel opening date.

WSDOT says construction on other areas of the project are underway despite the digging delays.

“We’re disappointed by this delay, but believe the schedule is moving in the right direction,” says a release from WSDOT. “We’re also focused on the bigger picture, which includes more than $750 million worth of work at the tunnel portals and elsewhere along the SR 99 corridor. That construction is not affected by the tunneling stoppage and continues full speed ahead.”

Todd Trepaneer, with Washington State Department of Transportation, maintains that this additional delay will not cost the taxpayers any additional money since the contract puts the entire responsibility for delay-related cost overruns on STP.

“Remember this is a fixed-price contract and Seattle Tunnel Partners has the obligation to complete this tunnel and the project for the price that they bid and that is still the plan,” says Trepaneer. “Right now it would be the same cost as the taxpayers were expecting at the beginning of the project.”

The tunnel will eventually carry Highway 99 traffic and allow the removal of the aging Alaskan Way Viaduct along the Seattle waterfront.

The Associated Press contributed to this report.

Please follow our Community Guidelines

MyNorthwest News

Bothell Fred Meyer fire arson arrest...

MyNorthwest Staff

Bothell Police arrest arson suspect in Fred Meyer fire near Thrasher’s Corner

Bothell Police arrested a suspect in connection with last week's fire at the Fred Meyer near Thrasher's Corner shortly after 7 a.m. this morning.

12 minutes ago

wa gas prices...

MyNorthwest Staff

WA gas prices surge as one county nears $6 a gallon

The price per gallon of gasoline in Washington sharply rose compared to one month ago, adding more than 18 cents to the state's average.

1 hour ago

SeaTac drug ring trafficking...

KIRO 7 News Staff

Man with decades-long history of domestic violence sentenced to 5 years for ‘vicious assault’

A Lummi Nation man with a decades-long history of domestic violence was sentenced to five years in federal prison for strangling his former partner.

2 hours ago

Snohomish train car collision...

Jason Sutich

Car struck by train in Snohomish County shuts down road after driver goes around crossing arms

A car was struck by a train in Snohomish County early Thursday morning after it drove around the lowered railroad crossing arms.

3 hours ago

bellevue i-405 i-90 ramp close...

Jason Sutich

NB I-405 ramp to EB I-90 in Bellevue reopens hours after semi carrying garbage overturned

The northbound I-405 ramp to eastbound I-90 in Bellevue is fully blocked after a semi-truck carrying garbage overturned on the roadway.

3 hours ago

Andre Sayles (2) bite of seattle shooting suspect...

Charlie Harger

Harger: SPD described a Georgetown stabbing suspect down to his jacket. For the Bite of Seattle shooters? Nothing.

Here's what SPD has released about the shooters who opened fire into a crowd at the Bite of Seattle on July 26, killing two bystanders: nothing.

3 hours ago

Bertha not expected to resume digging Seattle tunnel until late March 2015