MYNORTHWEST NEWS

Bertha’s 120-foot drop completed, but it’s not off the hook just yet

Aug 24, 2015, 7:43 AM | Updated: Aug 26, 2015, 7:45 am

Bertha’s front end is removed from the pit in March. (WSDOT)...

Bertha's front end is removed from the pit in March. (WSDOT)

(WSDOT)

The two-day job to reunite Bertha with its front end has concluded, but the massive face of the machine is not off the hook just yet.

While the 2,000 ton front end completed its journey to the bottom of the 120-foot access pit Tuesday afternoon, it remains connected to the crane. It will remain suspended as crews reconnect wires and hoses between the face and the body of the boring machine.

The Washington State Department of Transportation noted Monday that there was no set schedule to lower the massive front end into the pit where the body of Bertha remains sticking out of a wall. It did estimate that it could take 14 hours. In the end, it took all of Monday and Tuesday morning.

Bertha’s front end is composed of a cutterhead, motors, and a new main bearing assembly. Bertha also had new motors installed over the weekend.

By 5:30 p.m. Monday, the massive front end was only part way down the pit. The crane crews took a break overnight, and plan to continue the cutterhead’s journey Tuesday.

Next up, three pieces of Bertha’s outer shield are expected to be moved into the pit. Those pieces will be reassembled at the bottom. Bertha will then go through testing to ensure it is ready to drill again.

Mammoet is the company hired for the colossal move. The company specializes in heavy lifts and has previously lifted a Russian nuclear submarine from the floor of the Barents Sea. Mammoet’s crane is supplied with seven miles of steel cable and can handle up to 2,400 tons.

Please follow our Community Guidelines

MyNorthwest News

Seattle Police bonuses hiring incentives...

Frank Lenzi

Seattle Police Department scraps $50K hiring bonuses Sept. 1 as staffing crisis deepens

The Seattle Police Department (SPD) will no longer offer hiring bonuses as of September 1, citing budget concerns.

9 hours ago

man killed goose...

Jack Bilyeu, KIRO 7 News

Seattle Animal Shelter looking for man who killed goose at South Lake Union

The Seattle Animal Shelter is investigating an animal cruelty case after a man killed a goose on South Lake Union.

9 hours ago

Sound Transit Light Rail Fare Gates...

Frank Lenzi

Sound Transit approves fare gates at 14 light rail stations, eyes up to $83M in new revenue

Sound Transit plans to bring fare gates to up to 14 of its light rail stations — a move that could generate nearly $83 million a year in net revenue.

9 hours ago

brush fire SR 104...

Jason Sutich

Overnight closure likely on SR 104 after brush fire spreads to wires in Jefferson County

The westbound direction of SR 104 near Southpoint Road is blocked Thursday due to a brush fire that has spread to telephone wires.

10 hours ago

paddleboarder Lake Washington...

KIRO Newsradio staff

Paddleboarder in critical condition after being pulled from Lake Washington

A paddleboarder is in critical condition after being pulled from Lake Washington.

10 hours ago

wildfire JBLM washington soldiers...

Tim Hohl

Washington native leads JBLM soldiers into wildfire fight

Roughly 240 active-duty soldiers from JBLM are helping fight one of Washington’s biggest wildfires. The colonel overseeing them is a Washington native.

11 hours ago

Bertha’s 120-foot drop completed, but it’s not off the hook just yet