Eastside approach to 520 bridge opens summer 2014

Nov 11, 2013, 8:26 AM | Updated: 9:50 am

The more than $300 million Eastside approach work stretches from I-405 to the bridge entrance. The ...

The more than $300 million Eastside approach work stretches from I-405 to the bridge entrance. The work includes sound walls, fish passage, landscaping and an extensive system of bike-pedestrian trails. (WSDOT Photo)

(WSDOT Photo)

Driving across Lake Washington on State Route 520, you don’t see much progress toward construction of a new floating bridge. Some pilings are visible and a few concrete pontoons sit anchored offshore. The new bridge is not due to open until late 2015 at the earliest. But just to the east, a three-year highway project is nearing the finish.

Commuters headed to and from the bridge have been dealing with the loss of the carpool lane, temporary ramps and exits and re-configured lanes snaking through an active construction project.

“It’s certainly a challenge, for the commuters but even more importantly for the local communities,” said Fred Tharp, project director for the Washington State Department of Transportation.

“This is where they live and they need to drive through, they need to live with the construction noise and that’s been a challenge.” But it’s getting better said Tharp. “Every day, three times a day, I drive this project and I can see on a daily basis the amount of progress we’re making.”

The more than $300 million Eastside approach work stretches from I-405 to the bridge entrance.

“From one end of the corridor to the other, which is 2.5 miles, you’ll see new transit facilities, not just one but two new transit facilities, we have three large, lidded areas to reconnect the communities,” said Tharp, standing above the highway project at Evergreen Point.

The work includes sound walls, fish passage, landscaping and an extensive system of bike-pedestrian trails.

Final paving is not done but Tharp says right now the highway lanes essentially follow the final path of the highway.

“You will start seeing that final shape of the highway emerging in the spring, you’ll get two lanes each direction with large shoulders,” explained Tharp. “They will then be commissioning the transit facilities into operation and then opening up the H.O.V. lane at that time.”

Originally, the new floating bridge was supposed to open by the end of next year. That’s now delayed, possibly into 2016. The new Eastside approach is on schedule to open next summer.

MyNorthwest News

A Coast Guardsman tosses a rope to a kayaker in distress after the kayaker's boat overturned north ...

Tom Brock

San Juan Islands Rescue: Coast Guard crews save man after his kayak overturns

A Coast Guard helicopter and rescue boat saved a man from the chilly waters of the Salish Sea Friday, after his kayak capsized near Orcas Island.

5 hours ago

Boeing (2)...

Tom Brock

Software glitch raises safety concerns for Boeing 737 MAX planes

Boeing has notified its customers of a computer glitch on its 737 MAX planes that could force pilots to land manually, instead of using autopilot.

6 hours ago

seattle ranking cities...

MyNorthwest Staff

Seattle earns 4th-highest ranking in the world in new study of 1,000 cities

A new study ranks Seattle 4th globally, highlighting governance, economics, and quality of life among cities.

10 hours ago

parenting...

Katrina Guischard

The parenting advice going viral right now: be the pilot, not the passenger

An expert is challenging some of today's most popular parenting trends, and it's striking a chord.

1 day ago

ritzville i-90 closed visibility...

Jason Sutich

I-90 in Ritzville reopens after dust storm caused multiple collisions

I-90 in Ritzville has reopened after both directions were blocked Friday due to multiple collisions.

2 days ago

Ballard hit-and-run...

KIRO Newsradio staff

20-year-old sentenced to more than 3 years for deadly 2025 Ballard hit-and-run

The man accused in the hit-and-run death of a pedestrian in Ballard last year has been sentenced to more than three years in prison.

2 days ago

Eastside approach to 520 bridge opens summer 2014