Eastside approach to 520 bridge opens summer 2014

Nov 11, 2013, 8:26 AM | Updated: 9:50 am

The more than $300 million Eastside approach work stretches from I-405 to the bridge entrance. The ...

The more than $300 million Eastside approach work stretches from I-405 to the bridge entrance. The work includes sound walls, fish passage, landscaping and an extensive system of bike-pedestrian trails. (WSDOT Photo)

(WSDOT Photo)

Driving across Lake Washington on State Route 520, you don’t see much progress toward construction of a new floating bridge. Some pilings are visible and a few concrete pontoons sit anchored offshore. The new bridge is not due to open until late 2015 at the earliest. But just to the east, a three-year highway project is nearing the finish.

Commuters headed to and from the bridge have been dealing with the loss of the carpool lane, temporary ramps and exits and re-configured lanes snaking through an active construction project.

“It’s certainly a challenge, for the commuters but even more importantly for the local communities,” said Fred Tharp, project director for the Washington State Department of Transportation.

“This is where they live and they need to drive through, they need to live with the construction noise and that’s been a challenge.” But it’s getting better said Tharp. “Every day, three times a day, I drive this project and I can see on a daily basis the amount of progress we’re making.”

The more than $300 million Eastside approach work stretches from I-405 to the bridge entrance.

“From one end of the corridor to the other, which is 2.5 miles, you’ll see new transit facilities, not just one but two new transit facilities, we have three large, lidded areas to reconnect the communities,” said Tharp, standing above the highway project at Evergreen Point.

The work includes sound walls, fish passage, landscaping and an extensive system of bike-pedestrian trails.

Final paving is not done but Tharp says right now the highway lanes essentially follow the final path of the highway.

“You will start seeing that final shape of the highway emerging in the spring, you’ll get two lanes each direction with large shoulders,” explained Tharp. “They will then be commissioning the transit facilities into operation and then opening up the H.O.V. lane at that time.”

Originally, the new floating bridge was supposed to open by the end of next year. That’s now delayed, possibly into 2016. The new Eastside approach is on schedule to open next summer.

MyNorthwest News

2 street flooding...

James Lynch

Seattle Public Utilities prepares for street flooding as heavy rain approaches

Falling leaves and heavy rain can clog storm drains, causing street flooding and creating hazards for drivers, pedestrians, homes, and businesses.

15 minutes ago

Saldaña King County...

KIRO Newsradio staff

Rebecca Saldaña remains far ahead of Toshiko Hasegawa in King County Council race

Rebecca Saldaña holds a 21-point lead in the race for King County Council District 2, with 60% of votes counted in initial results Tuesday.

11 hours ago

Kim Schrier...

MyNorthwest Staff

Kim Schrier maintains early advantage over Spencer Meline in WA-8 race

Democratic incumbent Kim Schrier is ahead of Republican Spencer Meline in initial election results for Washington’s 8th Congressional District seat in the U.S. House of Representatives.

11 hours ago

adam smith doug basler sawant...

Frank Sumrall

Adam Smith keeps commanding lead over Doug Basler in WA-9 results

Democratic incumbent Adam Smith holds a commanding lead over Republican challenger Doug Basler in initial results for Washington’s 9th Congressional District.

12 hours ago

mckinney duresky Congressional District 4...

Frank Sumrall

Trump-endorsed McKinney continues to lead Duresky in WA District 4 to replace Newhouse

Republican Amanda McKinney leads Democrat John Duresky in initial results for Washington’s 4th Congressional District seat in the U.S. House of Representatives.

12 hours ago

Marie Gluesenkamp Pérez john braun primary...

Frank Sumrall

Marie Gluesenkamp Perez’s lead over John Braun barely budges in updated District 3 results

Democratic incumbent Marie Gluesenkamp Pérez leads Republican challenger John Braun in initial results for Washington’s 3rd Congressional District seat in the U.S. House of Representatives.

12 hours ago

Eastside approach to 520 bridge opens summer 2014