Emergency contract speeds bridge replacement

Jun 19, 2013, 3:22 PM | Updated: Jun 20, 2013, 6:32 am

A temporary span erected over the Skagit River on I-5 took less than a month to complete. (KIRO Rad...

A temporary span erected over the Skagit River on I-5 took less than a month to complete. (KIRO Radio/Brandi Kruse)

(KIRO Radio/Brandi Kruse)

The collapse of the I-5 Skagit River Bridge shows how fast government can work in an emergency. A replacement bridge was finished in less than a month. You might wonder why every transportation project can’t get done like that.

Within hours of the collapse May 23, the state was working on a plan.

“We’ve already got our bridge designers and engineers starting to work on what are the options for replacing this,” said Washington State Department of Transportation Secretary Lynn Peterson the next day.

Peterson called on trusted, pre-qualified contractors to do the initial work. Governor Jay Inslee vowed to re-open I-5 by mid-June.

And they did it. By awarding an emergency contract. Bart Treece, with the Washington State Department of Transportation says in an emergency, competitive bidding is suspended.

“We have laws, competitive bidding laws in this state, to make sure that it’s fair for folks to bid on and, of course, there’s the permitting process. But with the emergency contract we can streamline the permitting process and get a lot of agencies on board early on,” said Treece.

The Governor estimated a cost of $15 million for a temporary and then a replacement bridge. Typically, emergency contracts are expensive, due to fewer bidders, short notice and more costly supplies.

“We’re really happy that it came in under that $15 million number and that’s for both the temporary and the permanent structures,” Treece said. He pointed out that the state is not reluctant to issue emergency contracts. “It’s not that rare. A bridge collapse, that’s something that a lot of people hear about and that’s a major deal but you’ve got rock slides, you’ve got concrete panels cracking and you’ve got a lot of really delicate infrastructure that’s really old.”

It took 26 days to install a temporary Skagit River Bridge. But even with emergency contracting, the permanent bridge won’t open until sometime in October.

MyNorthwest News

costco boon boona coffee renton...

MyNorthwest Staff

Renton-based coffee company lands deal to be sold in Puget Sound Costco locations

Renton-based Boon Boona Coffee is headed to Costco. The East African coffee roaster has landed a deal to sell its Bereka Blend in eight Puget Sound warehouses.

19 minutes ago

fire semi-truck crash Kittitas county...

MyNorthwest Staff

Semi-truck crash causes fire on eastbound I-90 in Kittitas County Tuesday

A single semi-truck crashed on eastbound I-90 Tuesday afternoon, causing a fire.

2 hours ago

mt. baker highway winter...

KIRO 7 News Staff

Mt. Baker Highway closed Wednesday and Thursday, prepping for winter

Both directions of Mt. Baker Highway (SR 542) will be closed on Wednesday, Sept. 30, and Thursday, Oct. 1, from 7:30 a.m. to 4 p.m.

2 hours ago

wdfw black bear poach oso...

Frank Sumrall

WDFW seeks public’s help identifying two men who allegedly poached black bear in Oso

The Washington Department of Fish and Wildlife (WDFW) is searching for two men allegedly caught on camera hunting while trespassing on private property.

3 hours ago

costco churro...

MyNorthwest Staff

Costco brings back beloved food court item for first time since 2024

Churros will return to every U.S. location for a limited time. Costco’s chief financial officer, Gary Millerchip, confirmed the news during an earnings call.

4 hours ago

supreme court election...

Brandon Thompson, KIRO 7 News

Majority of WA Supreme Court seats are up for election: How to inform your vote

Washington voters may shift the balance of the Washington Supreme Court as five seats are open or up for reelection in November.

4 hours ago

Emergency contract speeds bridge replacement