Emergency contract speeds bridge replacement

Jun 19, 2013, 3:22 PM | Updated: Jun 20, 2013, 6:32 am

A temporary span erected over the Skagit River on I-5 took less than a month to complete. (KIRO Rad...

A temporary span erected over the Skagit River on I-5 took less than a month to complete. (KIRO Radio/Brandi Kruse)

(KIRO Radio/Brandi Kruse)

The collapse of the I-5 Skagit River Bridge shows how fast government can work in an emergency. A replacement bridge was finished in less than a month. You might wonder why every transportation project can’t get done like that.

Within hours of the collapse May 23, the state was working on a plan.

“We’ve already got our bridge designers and engineers starting to work on what are the options for replacing this,” said Washington State Department of Transportation Secretary Lynn Peterson the next day.

Peterson called on trusted, pre-qualified contractors to do the initial work. Governor Jay Inslee vowed to re-open I-5 by mid-June.

And they did it. By awarding an emergency contract. Bart Treece, with the Washington State Department of Transportation says in an emergency, competitive bidding is suspended.

“We have laws, competitive bidding laws in this state, to make sure that it’s fair for folks to bid on and, of course, there’s the permitting process. But with the emergency contract we can streamline the permitting process and get a lot of agencies on board early on,” said Treece.

The Governor estimated a cost of $15 million for a temporary and then a replacement bridge. Typically, emergency contracts are expensive, due to fewer bidders, short notice and more costly supplies.

“We’re really happy that it came in under that $15 million number and that’s for both the temporary and the permanent structures,” Treece said. He pointed out that the state is not reluctant to issue emergency contracts. “It’s not that rare. A bridge collapse, that’s something that a lot of people hear about and that’s a major deal but you’ve got rock slides, you’ve got concrete panels cracking and you’ve got a lot of really delicate infrastructure that’s really old.”

It took 26 days to install a temporary Skagit River Bridge. But even with emergency contracting, the permanent bridge won’t open until sometime in October.

Please follow our Community Guidelines

MyNorthwest News

seattle police interim chief katie wilson...

Nia Bliss, KIRO 7 News

Seattle Police Officers Guild praises interim chief appointment while criticizing mayor’s actions

Seattle Mayor Katie Wilson announced the appointment of Deputy Chief Andre Sayles to the Interim Chief role effective Friday.

30 minutes ago

wa electricity bill PSE...

MyNorthwest Staff

Washington AG Nick Brown fights back against PSE’s proposed 29% electric, 20% gas rate hikes

Washington Attorney General Nick Brown is pushing back against proposed utility rate hikes from Puget Sound Energy (PSE).

41 minutes ago

Mariners jimothy seattle...

Jason Sutich

Due to high demand, second ‘Jimothy Night’ for Seattle Mariners coming in August

The Seattle Mariners are hosting a second "Jimothy Night" next month after the first day themed around the celebrity raccoon sold out.

2 hours ago

level 3 evacuation chelan county fire...

KIRO 7 News Staff

Level 3 evacuation orders issued for areas of Entiat Valley of Chelan County for Little Giant Fire

Level 3 ‘Go Now’ evacuation orders have been issued for an area in Chelan County impacted by the Little Giant Fire.

3 hours ago

Seafair...

Paul Holden

Seafair weekend is here — but so are a lot more events around the Seattle area!

July is coming to a close, and that means that the countdown is on to get all those things on your summer bucket list crossed off!

4 hours ago

Andre Sayles...

KIRO 7 News Staff

Who is Andre Sayles? What we know about Seattle’s new interim police chief

Seattle Mayor Katie Wilson announced on Thursday that she has accepted the resignation of Seattle Police Chief Shon Barnes.

15 hours ago

Emergency contract speeds bridge replacement