Emergency contract speeds bridge replacement

Jun 19, 2013, 3:22 PM | Updated: Jun 20, 2013, 6:32 am

A temporary span erected over the Skagit River on I-5 took less than a month to complete. (KIRO Rad...

A temporary span erected over the Skagit River on I-5 took less than a month to complete. (KIRO Radio/Brandi Kruse)

(KIRO Radio/Brandi Kruse)

The collapse of the I-5 Skagit River Bridge shows how fast government can work in an emergency. A replacement bridge was finished in less than a month. You might wonder why every transportation project can’t get done like that.

Within hours of the collapse May 23, the state was working on a plan.

“We’ve already got our bridge designers and engineers starting to work on what are the options for replacing this,” said Washington State Department of Transportation Secretary Lynn Peterson the next day.

Peterson called on trusted, pre-qualified contractors to do the initial work. Governor Jay Inslee vowed to re-open I-5 by mid-June.

And they did it. By awarding an emergency contract. Bart Treece, with the Washington State Department of Transportation says in an emergency, competitive bidding is suspended.

“We have laws, competitive bidding laws in this state, to make sure that it’s fair for folks to bid on and, of course, there’s the permitting process. But with the emergency contract we can streamline the permitting process and get a lot of agencies on board early on,” said Treece.

The Governor estimated a cost of $15 million for a temporary and then a replacement bridge. Typically, emergency contracts are expensive, due to fewer bidders, short notice and more costly supplies.

“We’re really happy that it came in under that $15 million number and that’s for both the temporary and the permanent structures,” Treece said. He pointed out that the state is not reluctant to issue emergency contracts. “It’s not that rare. A bridge collapse, that’s something that a lot of people hear about and that’s a major deal but you’ve got rock slides, you’ve got concrete panels cracking and you’ve got a lot of really delicate infrastructure that’s really old.”

It took 26 days to install a temporary Skagit River Bridge. But even with emergency contracting, the permanent bridge won’t open until sometime in October.

Please follow our Community Guidelines

MyNorthwest News

Department of Energy...

MyNorthwest Staff

‘Deeply disturbing’: Department of Energy employee allegedly acquired explosive materials in attempt to aid Houthis

A Department of Energy employee was arrested and charged with attempting to provide material or resources to the Houthis.

37 minutes ago

paine field plane crash (1)...

MyNorthwest Staff

Small plane crashes in Everett, injuries reported

A small plane crashed on the west side of Paine Field in Everett Thursday afternoon.

2 hours ago

bats...

Tim Hohl

Crews narrow search for bats’ entry point after 8 found at Puyallup school

Another bat has been found inside a Puyallup elementary school, bringing the total to eight since mid-September.

2 hours ago

chelan hills fire suspect (2)...

Tim Hohl

Chelan Hills Fire suspect pleads not guilty, bail cut in half

A 19-year-old man arrested in connection with the deadly Chelan Hills Fire has pleaded not guilty to all nine felony charges against him.

3 hours ago

_SR-71 Blackbird...

Charlie Harger

Harger: Seattle’s Museum of Flight has a Blackbird. NASA is quietly trying to fly an SR-71 again after 27 years

NASA appears to be trying to fly an SR-71 Blackbird again after 27 years, but missing parts, fuel, and aging expertise make a comeback daunting.

3 hours ago

mayor katie wilson...

Luke Duecy

Political credit before public safety? Inside Mayor Katie Wilson’s gun violence strategy, disputed quotes and stakeholder concerns

Seattle Mayor Katie Wilson’s gun violence plan raises questions about disputed quotes and transparency.

3 hours ago

Emergency contract speeds bridge replacement