Bertha’s schedule is once again being pushed back by one month. (WSDOT)...

Bertha's schedule is once again being pushed back by one month. (WSDOT)

(WSDOT)

Bertha’s schedule is once again being pushed back.

The boring machine that has faced damage and a slew of delays was slated to start boring under Seattle in late November. That deadline has now been pushed back to late December.

Related: The Bertha blame game begins with a lawsuit

“STP has told us the changes in the schedule reflect the current emphasis on giving crews the time they need to complete the tunneling machine repairs successfully,” the Washington State Department of Transportation states on its website.

The schedule for Bertha is updated each month, the latest change was announced Oct. 22.

“Like all large construction projects, the schedule for this project changes frequently. WSDOT cannot verify any of the dates shown in this schedule.”

Related: What Bertha needs to do to begin boring again

The tunnel that would replace the Alaskan Way Viaduct is now expected to open in April 2018. It was originally expected to open this year.

Bertha broke down in Dec. 2013 about 1,000 feet into its 9,000 foot journey from SoDo to South Lake Union.

MyNorthwest News

Seattle Police bonuses hiring incentives...

Frank Lenzi

Seattle Police Department scraps $50K hiring bonuses Sept. 1 as staffing crisis deepens

The Seattle Police Department (SPD) will no longer offer hiring bonuses as of September 1, citing budget concerns.

4 hours ago

man killed goose...

Jack Bilyeu, KIRO 7 News

Seattle Animal Shelter looking for man who killed goose at South Lake Union

The Seattle Animal Shelter is investigating an animal cruelty case after a man killed a goose on South Lake Union.

4 hours ago

Sound Transit Light Rail Fare Gates...

Frank Lenzi

Sound Transit approves fare gates at 14 light rail stations, eyes up to $83M in new revenue

Sound Transit plans to bring fare gates to up to 14 of its light rail stations — a move that could generate nearly $83 million a year in net revenue.

4 hours ago

brush fire SR 104...

Jason Sutich

Overnight closure likely on SR 104 after brush fire spreads to wires in Jefferson County

The westbound direction of SR 104 near Southpoint Road is blocked Thursday due to a brush fire that has spread to telephone wires.

5 hours ago

paddleboarder Lake Washington...

KIRO Newsradio staff

Paddleboarder in critical condition after being pulled from Lake Washington

A paddleboarder is in critical condition after being pulled from Lake Washington.

6 hours ago

wildfire JBLM washington soldiers...

Tim Hohl

Washington native leads JBLM soldiers into wildfire fight

Roughly 240 active-duty soldiers from JBLM are helping fight one of Washington’s biggest wildfires. The colonel overseeing them is a Washington native.

6 hours ago

Seattle’s Bertha has been delayed once again