Tough time for crews digging in front of stalled Bertha to make repairs

Jul 28, 2014, 5:44 AM | Updated: Jul 29, 2014, 10:32 am

Digging under Seattle, as crews have learned the hard way, is not easy to do.

The Seattle tunnel drilling machine, Bertha, has been stalled since December of 2013, and now workers are having trouble with the repair pit.

The 120-foot deep pit in front of the giant tunneling machine is harder to dig than expected.

The Seattle Times reports workers are having so much trouble with the pit that it could delay the removal of the 2,000 ton cutter head.

The cutter head removal had been scheduled for late September or October.

The Washington State Department of Transportation said the work is taking longer than expected because crews have to install 11 additional piles, bringing the total to 84. As it is, WSDOT said Seattle Tunnel Partners crews are “working around-the-clock, seven days a week to complete the approximately 31 remaining piles.”

WSDOT said reinforcing the pit with large interlocking piles take longer to install in the self-supporting pit than standard piles.

According to WSDOT, the issues won’t delay the restart of tunnel digging, which is set to begin in March 2015, because Seattle Tunnel Partners built some wiggle-room into the project schedule.

The tunneling machine only made it about 1,000 feet before breaking down in December. The main bearing that drives the machine was damaged and the seals that protect it were leaking.

The state had two options to fix the world’s largest drill, either take it apart and reach the cutter head from the back or dig a pit in front and remove it. Seattle Tunnel Partners chose option B and started digging a giant pit in front of the drill.

WSDOT said crews are working on other areas of the repair schedule while the piles are being built:

-The main bearing has arrived and crews will likely begin its assembly closer to when it’s need this fall.
-The new out seal ring, the thrust seal ring, and bearing block are nearing completion and will be shipped to Seattle after they’re inspected.
-Crews will begin assembling two large crawler cranes in September that will ultimately lift the largest parts of Bertha from the access pit.
-From July through fall, crews will begin assembling the modular lift tower.

The drill is currently stuck in the mud just south of the Alaskan Way Viaduct.

MyNorthwest News

Fire crews respond to a helicopter hard landing after the aircraft's engine reportedly lost power n...

Tom Brock

Two aircraft emergencies in Pierce County Saturday

Two aircraft emergencies in Pierce County Saturday resulted in injuries to one pilot. 

11 hours ago

All lanes of SB I-5 near US 12 (MP 68) were blocked Saturday night due to a multi-vehicle collision...

Tom Brock

Power restored to thousands of homes and businesses after powerful windstorm hits Pacific Northwest

Tens of thousands of homes and businesses are in the dark this morning after strong winds and heavy rain from a storm blew through the Pacific Northwest.

14 hours ago

Rhone Bellevue Square Activewear Award Winning holiday shopping...

Regan Gallo-Fenz

Activewear brand Rhone opens in Bellevue just in time for holiday shopping season

Activewear brand Rhone officially opened its first Washington store in Bellevue on Friday. The new location is the brand's fourth West Coast store.

17 hours ago

rent a mom...

Katrina Guischard

Rent a mom for your college kid? Some parents are spending up to $2,500

These days, some parents aren't just sending their kids off to college with a laptop and a laundry bag — they're sending money to rent a mom!

17 hours ago

This NOAA satellite image shows the magnitude of the storm moving inland from the Pacific Ocean. (P...

Ted Buehner, KIRO Newsradio Meteorologist

What to expect as Western Washington’s first big fall storm arrives Saturday night

The fall season’s first strong weather system will sweep through Western Washington tonight, bringing strong winds and rain.

1 day ago

Pierce County man sentenced child sex crimes...

Regan Gallo-Fenz

Pierce County man sentenced to 15 years in federal prison for child sex crimes

A Pierce County man has been sentenced to 15 years in federal prison after attempting to arrange the sexual abuse of children and producing child sexual abuse material, federal prosecutors announced.

2 days ago

Tough time for crews digging in front of stalled Bertha to make repairs