SpaceXAI started Southaven data center construction without water permits, Mississippi alleges

Nov 6, 2026, 1:55 PM | Updated: 2:48 pm

Mississippi’s environmental regulators released details this week on a set of penalties against SpaceXAI for violating state water pollution laws by starting construction on its Southaven data center facilities without needed permits.

The company first announced the potential fines to investors two weeks ago, speculating the amount could reach as much as $6.1 million.

To limit pollution from construction reaching public bodies of water, state law requires companies to first obtain a permit. Without proper protections, rain, for instance, can carry debris and chemicals off construction sites and pollute natural habitats, drinking water systems and recreational areas, federal regulators warn.

Earlier this year, SpaceXAI – through its subsidiary, MZX Tech LLC – asked the Mississippi Department of Environmental Quality for permits allowing construction within its growingSouthaven footprint, which includes a power plant as well as land to build a $20 billion data center facility called MACROHARDRR.

But during a July meeting between MDEQ and MZX Tech, “it became apparent” the company had already begun construction on the land in question, impacting about 30 acres, MDEQ records show.

On July 16, a day after the meeting, MDEQ staff visited Southaven and confirmed the infractions. The agency sent twonotices of violation to MZX Tech on Aug. 10, both of which “will be subject to the maximum statutory penalty” of $25,000 for each day construction continues without the needed permits, MDEQ wrote.

“The Company is cooperating with MDEQ and is in discussions to resolve the matters through a single agreed order,” SpaceXAI wrote in its Oct. 22 filing with the Securities and Exchange Commission.

It’s unclear where the $6.1 million figure came from. Based on the $25,000-per-day figure, it could suggest the violations lasted for several months. But MDEQ declined to say if the amount was accurate, citing its policy not to comment on pending enforcement matters.

At one of the MZX Tech properties, a former Southaven training facility that neighbors Horn Lake Creek, MDEQ staff found that “no steps have been taken to protect stormwater infrastructure at the site,” and that there was a lack of protection against “fugitive dust emissions.”

At the 2400 Stateline Road property, the site for MACROHARDERR, the staff found “no controls around storm inlets.” The MDEQ inspectors noted that, while construction appeared to have started around the beginning of 2026, the property’s last construction storm water permit expired in 2023.

MDEQ responds to federal judge about its turbine exemptions

Last week, a federal judge found that MDEQ had misinterpreted federal clean air statutes when allowing SpaceXAI to run 69 temporary natural gas turbines without a permit. U.S. District Court Judge Debra Brown included the opinion in her ruling against a motion to dismiss the NAACP’s April lawsuit against the data center company.

MDEQ relied on a federal Clean Air Act exemption intended for mobile generators, and SpaceXAI’s turbines clearly did not meet that criteria, Brown reasoned. That distinction is a key focus of the NAACP’s argument against the company.

The agency responded to the order in a statement to Mississippi Today on Wednesday.

“MDEQ is aware of the Court’s order and takes seriously all opinions by a federal court,” agency spokesperson Jan Schaefer said. “Nonetheless, MDEQ is not a party to that case and the order is not binding upon the agency. Furthermore, that litigation is ongoing and subject to appeal so it is not final at this point.

“MDEQ always seeks to make sure our policies are in compliance with state and federal law and will do the same here once that litigation concludes.”

The agency first told the Elon Musk-owned company last year that it could run the generators without a permit because the units are “affixed to a portable unit (i.e., a flatbed trailer)” and are therefore considered mobile.

Brown, though, disagreed. She argued that, given the size of the generators and the fact they aren’t “self-propelled or intended to be propelled” while operating, the federal exemption for mobile sources can’t apply.

___

This story was originally published by Mississippi Today and distributed through a partnership with The Associated Press.

Please follow our Community Guidelines

National News

A display board shows canceled flights to the U.S., in Frankfurt, Germany, Saturday, Nov. 14, 2026....

Associated Press

What to know about flights after the US nationwide ground stop

A nationwide ground stop ended around 8:15 p.m. ET, and some domestic flights have now departed from U.S. airports. However, normalizing air traffic after the longest flight stoppage in 25 years will be slow, authorities warned. Officials say the system is likely to be operating normally in time to handle the Thanksgiving travel rush. Here’s […]

1 hour ago

The Emanuel Nine Memorial fountain is seen during a media preview at Mother Emanuel AME Church in C...

Associated Press

Memorial opens honoring victims of the 2015 Charleston church massacre

It took Alana Grant years to find the strength to set foot in the basement of Mother Emanuel AME Church in Charleston, where her grandfather, the Rev. Daniel Lee Simmons, attended his final Bible study. Her fears have been replaced by gratitude and hope now that there is a completed memorial in a courtyard by […]

6 hours ago

Associated Press

Thousands of flights canceled as airlines work to dig out from nationwide ground stop

WASHINGTON (AP) — More than 2,000 flights were canceled Saturday as airlines across the U.S. worked to dig out from the longest nationwide ground stop in 25 years, which stranded passengers and forced professional and college sports teams to scramble for alternate transportation. Trump administration officials said new technology being added to the nation’s air […]

6 hours ago

FILE - President Donald Trump talks with Defense Secretary Pete Hegseth after a roundtable on crimi...

Associated Press

With shifting Iran rhetoric following US elections, Trump leaves Mideast in limbo about path ahead

WASHINGTON (AP) — President Donald Trump has had a lot to say about his thinking on the way ahead in the Iran war since Republicans were trounced in last week’s midterm elections. In exchanges with reporters, broadcast interviews and social media posts since Election Day, he’s somehow managed to back away from carrying out additional […]

7 hours ago

Associated Press

Alaska voters reject ballot measure seeking to repeal open primaries, ranked voting system

JUNEAU, Alaska (AP) — Alaska voters have rejected the latest attempt to repeal the state’s system of open primaries and ranked choice voting in general elections. The ballot measure, decided as part of the Nov. 3 election, marked the second time in two years that voters have rejected attempts to overturn the system and revert […]

8 hours ago

FILE - Alaska gubernatorial candidate Jonathan Kreiss-Tomkins, a Democrat, speaks to people outside...

Associated Press

Kreiss-Tomkins becomes first Democrat since 1998 elected governor in Alaska

JUNEAU, Alaska (AP) — Alaska voters have elected a Democrat for governor for the first time since 1998, part of a national midterm elections wave that gave the party sweeping wins in state governments across the country. Former state lawmaker Jonathan Kreiss-Tomkins defeated three Republicans, including one endorsed by President Donald Trump. His victory means […]

8 hours ago

SpaceXAI started Southaven data center construction without water permits, Mississippi alleges