Climate Pledge Arena construction hits key milestone ahead of fall opening

Jan 27, 2021, 12:10 PM | Updated: Jan 29, 2021, 5:04 pm

Construction on Seattle’s Climate Pledge Arena hit a major milestone this week, as workers removed the last of temporary supports that were holding the iconic roof up while permanent supports were built.

Seattle Center arena roof ‘floating’ as work goes on beneath

The roof — which weighs 44 million pounds — had been supported by 72 temporary steel columns and a reinforcement structure for nearly a year to the date. Removing those columns was a complicated process that required meticulous and careful work.

“Now we’re in here, we’ve got less than 12 inches in many areas between new structures and temporary roof elements, we’ve got to get 55 thousand pounds of steel out of here without damaging the new structure,” said Mortenson Senior Project Manager Will Traylor.

“In a lot of ways it’s like climbing a mountain — it’s tough to go to the top, it’s just as tough on your way down,” OVG Construction Executive Ken Johnsen added.

Many on the project describe it as “one of the most complicated things they’ve ever worked on,” for a process Johnsen says is going “extremely well.”

Climate Pledge Arena — naming rights of which were purchased by Amazon in 2020 — is expected to open by fall 2021. Most of 2019 was spent excavating 600,000 cubic yards of dirt, a phase of the project that finished by the end of February 2020. Last year was more about building up, including adding steel framing for the arena’s walls.

Climate Pledge Arena: NHL Seattle arena name rights bought by Amazon

In addition to Seattle Kraken hockey and Seattle Storm WNBA basketball, the arena will host concerts and could also house a future Seattle NBA team. Capacity for NHL games sits at 17,100; concert capacity is up to 17,200, while basketball games could draw up to 18,100.

MyNorthwest News

Nisqually River Bridge...

MyNorthwest Staff

1 dead, car catches fire after ‘mechanical mishap’ on I-5 north at Nisqually River Bridge

A person was killed due to a "mechanical mishap" on northbound I-5 at the Nisqually River Bridge. A car subsequently caught fire.

5 hours ago

memorial day weekend travel SEA airport...

Michael Strite

SEA airport is shutting down the Spot Saver program

Seattle-Tacoma International Airport (SEA) will end the "SEA Spot Saver" program after Thanksgiving.

6 hours ago

Neil Gehring National Park Service...

Michael Strite

Search continues for missing hiker at Olympic National Park

26-year-old Neil Gehring left the Madison Falls Trailhead at Olympic National Park on Aug. 31. He was reported missing on Sep. 2.

7 hours ago

belltown shooting (3)...

Gee Scott and Ursula Reutin Show

‘People act and say things to get them elected’: Gee urges leaders to face families after Belltown shooting

A 21-year-old man who tried to stop a robbery during a Belltown street takeover was shot three times, then had to walk two blocks begging for help.

9 hours ago

tukwila...

Michael Strite

Tukwila police officers rescue man trapped underneath car

A man was taken to the hospital after he was trapped beneath a car early Thursday morning. Around 4 a.m., Tukwila police responded to a vehicle that went off the road along Interurban Ave. S. Officers found the car with a man pinned underneath. They were able to lift the car and rescue the victim. […]

9 hours ago

bellevue drone expands...

Lexi Herda, KIRO 7 News

Bellevue expands use of drones for city’s first responders

Bellevue is expanding its use of drones for its first responders.

10 hours ago

Climate Pledge Arena construction hits key milestone ahead of fall opening