CHOKEPOINTS

Failing expansion joint continues to plague I-90 on Mercer Island

Feb 20, 2024, 10:30 AM | Updated: 12:31 pm

It’s added 15-to-20 minutes to the drives of eastbound I-90 commuters. So why is it taking so long to fix the expansion joint on the freeway on Mercer Island?

Eastbound I-90 has been reduced to three lanes on the east end of Mercer Island for about a month now. There is a failing expansion joint on this section of road as I-90 crosses the East Channel Bridge.

The state decided to close the lane last month to keep vehicles off of it because engineers worried it could fail under loads.

The plan was to re-stripe a fourth lane back into the freeway sometime this month. All lanes would be reduced to 10-feet in width. And the expansion joint would be fixed and replaced next year.

More Chokepoints: SDOT experiments with freight/transit lane

I get a lot of comments about this, considering drivers are seeing up to 20 minute delays during rush hour. John Donaldson reached out to me last week, asking what a lot of people are: “Why is this taking so long, and why will it take until next year to fix it?”

He wrote this “hiccup” is costing him “15-to-20 minutes a day.”

I went a little deeper with the Washington Department of Transportation on this, and here is its response.

WSDOT is having trouble finding a contractor that can do the re-striping. There are not many that do this particular type of work. Once a contract is signed, the re-striping will be done as fast as possible.

As for why it will take another year to replace the failing joint, WSDOT said the project is still in the design phase. It has been declared an emergency, and the project has been moved up on the schedule as far as it can be.

More from Sully: Tacoma HOV expansion leaves 8-mile gap

The joint was originally scheduled to be replaced in 2027. It is now on the fast track to be done in 2025.

The new joints need to be custom-made and they will take four to six months to build.  2025 is the earliest WSDOT can pull this off.

I’m working with WSDOT closely, and I’ll let you know when that re-striping will be done.

Chris Sullivan is KIRO Newsradio’s Senior Transportation Reporter. Check out more of Chris’ Chokepoints.

Chokepoints

Amtrak...

Chris Sullivan

Amtrak opens new Seattle maintenance facility ahead of 2027 schedule

Amtrak has cut the ribbon on its new 100,000-square-foot maintenance facility in SODO, opening a building originally scheduled to debut in 2027.

2 days ago

Tacoma Narrows Bridge (2)...

Lexi Herda, KIRO 7 News

Expect major delays: Lanes closing on Tacoma Narrows Bridge for extensive repairs

Major lane closures are coming to the Tacoma Narrows Bridge, starting this weekend.

2 days ago

copper wire theft lighting lakewood...

Chris Sullivan

Wire theft knocks out more lighting along I-5 in Lakewood

Here we go again. Thieves who ripped wire from Washington State Department of Transportation electrical boxes impacted drivers in Lakewood earlier this week.

3 days ago

othello crash sr 24...

MyNorthwest Staff

11 injured in work bus, semi-truck crash on SR 24 near Othello

At least 11 people were injured in a "critical incident" after a work bus and semi-truck collision on SR 24 near Othello Thursday morning.

3 days ago

wa toll...

Chris Sullivan

Get ready, drivers: Puyallup to Lynnwood could cost $54 in tolls

We're less than a year from the expansion of the express toll lane system between Renton and Bellevue, marking the start of segmented tolling.

3 days ago

revive I-5 tolls I-405 commute...

Nate Connors

Revive I-5 on Ship Canal Bridge to end 2 months ahead of schedule

WSDOT announced it has moved up Revive I-5's completion date to the weekend of Oct. 30, which is two months ahead of schedule.

3 days ago

Failing expansion joint continues to plague I-90 on Mercer Island