Costly transportation program falling short on key items in Seattle

Apr 25, 2018, 11:17 AM | Updated: 11:18 am

SDOT, viadoom, bike lanes...

Proponents of Seattle bike lanes score a huge win. (SDOT)

(SDOT)

The City of Seattle doesn’t have enough money to complete transportation projects promised years ago.

SDOT: Streetcar project is, perhaps, an example of poor management

An assessment of the Levy to Move Seattle, a program funded by a $930 million transportation levy, found “cost estimates included in the original budget were insufficient to meet the levy commitment.”

Included in the “sub-programs” short on funding are pedestrian and bikes projects, street maintenance, and the plan to design high-priority bridge replacements.

During a meeting Tuesday, Seattle Department of Transportation’s interim Director reportedly said they do not have enough to do everything promised to the taxpayers. He added that cost estimates for some of the projects were insufficient.

The projects facing a funding shortfall include:

  • Constructing about 50 miles of protected bike lanes and 60 miles of greenways
  • Repairing up to 225 blocks of damaged sidewalks
  • Making curb ramp and crossing improvements at more than 700 intersections
  • Repaving up to 180 lane miles of streets
  • Repaving 65 targeted locations every year
  • Planning and designing high-priority bridge replacements to begin construction after 2024
  • Multimodal improvements, including the completion of seven RapidRide corridor projects
  • Build 150 new blocks of sidewalks

It’s currently unclear just how short the city is on fulfilling its promises.

Chokepoints: What slows you down each day?

Despite the shortfalls, the city notes more projects have been completed than not. You can read a full list of the projects on pages 3-4. Click here to read the report.

Seattle voters approved Move Seattle in 2015. SDOT assumed a total of $1.77 billion in funding, including the money from taxpayers, $285 in local funding, and $564 million in regional and federal grants, as well as partnerships.

MyNorthwest News

tenino guns explosives...

MyNorthwest Staff

69-year-old Tenino resident back in jail after guns, 1.5 pounds of explosives found in home

A 69-year-old Tenino-area man was arrested for violating his bail when law enforcement officials found guns and explosives in his home.

46 minutes ago

olympia berry stand close...

Jason Sutich

Spooner Berry Farms says city promised stand could stay in park plans, Olympia says that never happened

Spooner Berry Farms in Olympia may soon have to close up its berry shop along Yelm Highway after 47 years as the city has plans for a community park.

2 hours ago

school bus drivers zum seattle...

Frank Sumrall

Strike authorized for Seattle school bus drivers as contract dispute stalls

Hundreds of Seattle school bus drivers have authorized a strike amid a contract dispute with Zūm Transportation, the drivers' union confirmed.

2 hours ago

convention center paint...

Chris Sullivan

Exclusive Update: Painting of 9th Avenue is underway after Convention Center’s artful mess

The paint the Convention Center used to make the street look pretty couldn't be removed, keeping the road closed for weeks longer than the SDOT street closure permit allowed.

4 hours ago

expedia layoffs...

MyNorthwest Staff

Expedia cuts 58 Seattle jobs in second round of layoffs this year

Expedia Group is cutting 58 jobs in Seattle, according to a WARN notice filed by the company.

4 hours ago

Kitsap County Sheriff burning SUV crash...

KIRO 7 News Staff

Kitsap Co. deputies rescue man from burning SUV after police chase crash

The Kitsap County Sheriff’s Office posted body cam video of deputies rescuing a man they said crashed after speeding away from police before his car caught fire.

5 hours ago

Costly transportation program falling short on key items in Seattle