Aug 20, 2024, 6:37 AM

montlake lid sr 520...

A graphic rendering of the busy summer construction schedule for SR 520, including the Montlake Lid project. (Graphic rendering courtesy of WSDOT)

(Graphic rendering courtesy of WSDOT)

We’re down to the final checklists and finishing touches for the Montlake Lid Project on State Route 520 (SR 520).

There are just three more full closures of SR 520 related to the Montlake Lid Project. The full closures are needed to test all the systems inside the new lid and to finish the direct access ramps that will take transit up to the new station at Montlake.

That finishing work is vital in making sure everything is functioning properly.

Watch for the bump: New Everett HOV lane causing trouble for drivers

“Commissioning is verifying that all those systems work,” Steve Peer, a Media and Construction Communications Manager for the Washington Department of Transportation (WSDOT), said. “The lighting system works. The fire suppression system works. Does the drainage work after there’s been foam in case of a fire on 520? We have to make sure that this all works.”

Other parts of the corridor will also use the closure to get some work done.

“There’s some drilling work way to the west that the Portage Bay Bridge and Roanoke Lid folks are going to be doing,” Peer said. “They need an empty roadway to do that. There’s some sign bridge work. There’s lots of little finishing touches that need to happen this weekend.”

SR 520 will be closed in both directions from 11 p.m. Friday night until early Monday morning. The closure is at Interstate 5 (I-5) on the west side and 92nd on the east side. There will be no access to Montlake from SR 520. The trail will also be closed.

When will the project officially be done?

“What we’re looking for realistically is to have the lid operational at the end of October,” Peer said.

Drivers should get their second lane on the ramp to southbound I-5 a few weeks ahead of that, but there is a chance for that reversible ramp to the express lanes. That will not be opening any time soon. WSDOT had hoped to open that as soon as it was finished, but the Portage Bay work will be in the way.

“The crews need that for some staging,” Peer said. “It’s a safety issue.”

Once the Montlake Project finishes, attention will turn to the final piece of the 520 expansion. The final mile from Montlake, over Portage Bay, to I-5.

More from Chris Sullivan: Sound Transit preparing for Lynnwood light rail opening on Aug. 30

Even though the project is $700 million over budget, and that financing hasn’t been finalized, work is already underway on that section.

“As far as construction, it’s full speed ahead there,” Peer said.

Construction on that final piece of SR 520 will take seven or eight years. Detours, delays and closures aren’t going anywhere.

Check out more of Chris’ Chokepoints here. You can also follow Chris on X. Head here to follow KIRO Newsradio Traffic’s profile on X.

Chokepoints

US 2 Crash Monroe...

MyNorthwest Staff

US 2 reopens after multi-vehicle collision shuts down all lanes for nearly six hours

An early morning headache for drivers near Monroe. WSDOT says all lanes of US 2 are blocked in both directions near Monroe after a collision involving multiple vehicles.

8 hours ago

fish passage project...

Chris Sullivan

Massive fish passage project under I-90 in Factoria nearing its end

Eastbound I-90 drivers are close to getting their HOV lane back in Factoria. The fish passage project under the freeway is in its final months.

9 hours ago

3 - Tacoma Narrows Bridge...

KIRO 7 News Staff

Expect long PM commutes until further notice on the Tacoma Narrows Bridge

Drivers who use the Tacoma Narrows Bridge (SR 16) to Gig Harbor should expect longer nighttime commutes due to construction work.

21 hours ago

Amtrak...

Chris Sullivan

Amtrak opens new Seattle maintenance facility ahead of 2027 schedule

Amtrak has cut the ribbon on its new 100,000-square-foot maintenance facility in SODO, opening a building originally scheduled to debut in 2027.

4 days ago

Tacoma Narrows Bridge (2)...

Lexi Herda, KIRO 7 News

Expect major delays: Lanes closing on Tacoma Narrows Bridge for extensive repairs

Major lane closures are coming to the Tacoma Narrows Bridge, starting this weekend.

4 days ago

copper wire theft lighting lakewood...

Chris Sullivan

Wire theft knocks out more lighting along I-5 in Lakewood

Here we go again. Thieves who ripped wire from Washington State Department of Transportation electrical boxes impacted drivers in Lakewood earlier this week.

5 days ago

Counting down to Montlake Lid opening on SR 520