CHOKEPOINTS

Failing expansion joint continues to plague I-90 on Mercer Island

Feb 20, 2024, 10:30 AM | Updated: 12:31 pm

It’s added 15-to-20 minutes to the drives of eastbound I-90 commuters. So why is it taking so long to fix the expansion joint on the freeway on Mercer Island?

Eastbound I-90 has been reduced to three lanes on the east end of Mercer Island for about a month now. There is a failing expansion joint on this section of road as I-90 crosses the East Channel Bridge.

The state decided to close the lane last month to keep vehicles off of it because engineers worried it could fail under loads.

The plan was to re-stripe a fourth lane back into the freeway sometime this month. All lanes would be reduced to 10-feet in width. And the expansion joint would be fixed and replaced next year.

More Chokepoints: SDOT experiments with freight/transit lane

I get a lot of comments about this, considering drivers are seeing up to 20 minute delays during rush hour. John Donaldson reached out to me last week, asking what a lot of people are: “Why is this taking so long, and why will it take until next year to fix it?”

He wrote this “hiccup” is costing him “15-to-20 minutes a day.”

I went a little deeper with the Washington Department of Transportation on this, and here is its response.

WSDOT is having trouble finding a contractor that can do the re-striping. There are not many that do this particular type of work. Once a contract is signed, the re-striping will be done as fast as possible.

As for why it will take another year to replace the failing joint, WSDOT said the project is still in the design phase. It has been declared an emergency, and the project has been moved up on the schedule as far as it can be.

More from Sully: Tacoma HOV expansion leaves 8-mile gap

The joint was originally scheduled to be replaced in 2027. It is now on the fast track to be done in 2025.

The new joints need to be custom-made and they will take four to six months to build.  2025 is the earliest WSDOT can pull this off.

I’m working with WSDOT closely, and I’ll let you know when that re-striping will be done.

Chris Sullivan is KIRO Newsradio’s Senior Transportation Reporter. Check out more of Chris’ Chokepoints.

Chokepoints

fire semi-truck crash Kittitas county...

MyNorthwest Staff

Semi-truck crash causes fire on eastbound I-90 in Kittitas County Tuesday

A single semi-truck crashed on eastbound I-90 Tuesday afternoon, causing a fire.

19 hours ago

mt. baker highway winter...

KIRO 7 News Staff

Mt. Baker Highway closed Wednesday and Thursday, prepping for winter

Both directions of Mt. Baker Highway (SR 542) will be closed on Wednesday, Sept. 30, and Thursday, Oct. 1, from 7:30 a.m. to 4 p.m.

19 hours ago

Bellevue speed camera ticket...

Jason Sutich

Drivers can now be ticketed by Bellevue’s 4 new speed cameras

The grace period for the four new speed safety cameras in Bellevue ended, meaning drivers can now be ticketed for any infractions in the newly monitored zones.

2 days ago

US 101 ramp I-5 boat crash...

MyNorthwest Staff

US 101 ramp to northbound I-5 reopened after vehicle towing a boat crashes Near Olympia

The US 101 ramp to northbound I-5 was blocked for several hours due to a collision involving a vehicle towing a boat.

2 days ago

US 2 monroe gold bar wsdot...

Chris Sullivan

15 months of construction about to start on US 2 between Monroe and Gold Bar

WSDOT has a laundry list of improvements for the corridor, including new sidewalks, adding new pedestrian crossings, adding new signs, rumble strips, and a new roundabout in Sultan.

2 days ago

sr 167 fatal motorcycle crash auburn...

Jason Sutich

Southbound SR 167 in Auburn reopens after fatal motorcycle crash

All lanes of southbound SR 167 north of SR 18 in Auburn have reopened after a fatal collision Monday afternoon involving a motorcycle and a car.

3 days ago

Failing expansion joint continues to plague I-90 on Mercer Island