CHOKEPOINTS

A deep dive on the final stages of repair to the West Seattle Bridge

Aug 30, 2022, 8:20 AM | Updated: 8:29 am

bridge...

(KIRO 7)

(KIRO 7)

Load testing is one of the final steps to perform before the West Seattle Bridge can reopen to traffic. We’ve talked about it a little bit before, but it’s time for a deep dive.

It’s one thing to say engineers are going to put dump trucks full of rocks at key points on the bridge to test its strength. I wanted to hear from an actual engineer on the subject.

Residents celebrate West Seattle Bridge reopening, but still much to do

Greg Banks is the top engineer for this repair project. I met with him on the West Seattle Bridge during my tour inside the box girders Thursday. Banks said there will be static and dynamic testing, with those trucks being stationary and moving.

“We have six different load cases, and we’re positioning them at various locations,” he said. “Up to twelve trucks will be on the bridge at a time, but each of those trucks will weigh 80,000 pounds.  They’re strategically placed to create worst-case stress conditions.”

So what will Banks be looking for in these tests? He will be watching all the sensors which have been embedded in the bridge to make sure the numbers he sees are what he expects. Banks will be looking for an expansion of the concrete cracks under the load, and he’s looking for movement in the fractions of millimeters. That’s how small and precise this testing is.

What if the numbers don’t line up?

“If it doesn’t, then we go and look at the analytical prediction to make sure we didn’t mess something up with data input,” Banks said. “We’re going to make sure a sensor hasn’t popped or anything like that and is giving us faulty readings. We are going to ground-truth it first before we think it’s not behaving as expected.”

Heather Marx is the project director for the Seattle Department of Transportation. She expects this load testing to go as planned. Her confidence comes from the last two and a half years of the repair work, and the bridge has been responding as expected.

“When it was cold and we had a huge weight of snow on the bridge, it behaved as we expected it to,” she said.  “During the heat dome, the bridge behaved as we expected it to.  We have no expectation that any of those tests are going to come back anything other than exactly as anticipated.”

But if they do, Marx will not hesitate in delaying the reopening, which is now scheduled for September 18.

“We need to make sure,” she said.  “We are not going to open a bridge that isn’t safe for ordinary travel.”

You might find it interesting that live traffic doesn’t add that much weight to the bridge. Most of the weight stresses come from the weight of the bridge itself. Only about 20% of the weight comes from the vehicles using it.

Check out more of Chris’ Chokepoints.

Please follow our Community Guidelines

Chokepoints

ritzville i-90 closed visibility...

Jason Sutich

I-90 in Ritzville reopens after dust storm caused multiple collisions

I-90 in Ritzville has reopened after both directions were blocked Friday due to multiple collisions.

2 days ago

super load marysville...

Chris Sullivan

Super load stuck on I-5 south in Marysville should move tonight

A truck carrying a massive pre-fab building has been parked along the southbound I-5 ramp at 88th St. in Marysville for three days.

2 days ago

closure (1)...

MyNorthwest Staff

I-5 reopens in both directions between Maytown and Tumwater

I-5 has reopened in both directions in Thurston County at milepost 97, KIRO Newsradio confirmed.

2 days ago

oyster run anacortes...

Nate Connors

43rd annual Oyster Run returns this weekend in Anacortes

The Oyster Run welcomes thousands of motorcyclists to Skagit County by Figaldo Bay. It's loud, it's proud, and it takes over Anacortes this time each year.

3 days ago

sounder train shoreline...

MyNorthwest Staff

All S Line trains stopped after woman hit in SODO

All Sound Transit S Line trains have been stopped after a woman was hit in SODO Thursday.

3 days ago

Pinehurst Station light rail...

Chris Sullivan

Sound Transit to open new light rail station 5 years ahead of schedule

Sound Transit isn't known for being on time or on budget with its light rail projects, but it's about to open a new station way ahead of schedule.

3 days ago

A deep dive on the final stages of repair to the West Seattle Bridge