SR 99 tunnel is built. Why can’t we use it yet?

Nov 1, 2018, 5:47 AM | Updated: 7:19 am

seattle tunnel toll, SR 99...

A graphic depicting the north end of the tunnel once completed. (WSDOT)

(WSDOT)

Primary construction for the SR 99 tunnel has finally finished, with the project reaching what the Washington Department of Transportation calls “substantial completion.”

The substantial completion phase is an important distinction for the project, marking the point at which Seattle Tunnel Partners (STP) can officially hand the facility over to the Washington State Department of Transportation. The lanes are built, ventilation is working, and crews have even practiced responding to emergency scenarios inside the tunnel. WSDOT noted in a press release that “the tunnel could be technically operated as designed.”

So, what’s the hold up, and why can’t we start using the tunnel now?

There are a pair of additional milestones WSDOT much reach before the new SR 99 tunnel is officially ready. In short, crews have to build the roads that actually go into the tunnel. While the tunnel works, there’s currently no pathway for cars to drive into it. Or as WSDOT puts it:

What comes next is a variety of wrap-up work elements that, once completed, will result in the tunnel reaching the second milestone, known as ‘physical completion.’ Meanwhile, as STP works toward physical completion, WSDOT will continue to train maintenance and operations staff to ensure the tunnel and those responsible for its operation are ready to go in early 2019.

If you thought substantial and physical completion was exciting, just wait. Because after all that comes “final completion.” That’s achieved when the last bit of paperwork and documentation is finished and submitted — so perhaps not as exciting.

That said, the tunnel will actually open before final completion.

The tunnel will officially open in early 2019. Before that happens, there will be a three-week closure of SR 99 through downtown Seattle to realign the highway. Both the viaduct and the tunnel will be closed during this period. Additional ramp closures could mean up to six weeks of traffic disruption.

RELATED: How traffic will work after Seattle’s SR 99 tunnel opens

Please follow our Community Guidelines

Chokepoints

Sound Transit budget deficit delays...

John Curley Show

‘Almost no accountability’: Transportation expert says Sound Transit is ‘building for the past’ amid ballooning budget

KIRO host John Curley, a longtime skeptic of public transportation and its ballooning costs, brought on Charles Prestrud to discuss where Sound Transit went wrong.

1 day ago

SR 202...

Chris Sullivan

SR 202 near Fall City to close this weekend for emergency river embankment repairs

Work is moving to SR 202 near Fall City this week, creating a 16-mile detour for people trying to get around the area.

2 days ago

SR 20...

KIRO 7 News Staff

Westbound SR 20 closed for a semi-truck off the road

According to Trooper Kelsey Harding, shortly before 6:30 p.m. Monday, a semi-truck went off the road on SR 20 just east of SR 9.

2 days ago

SEA ground stop thunderstorm...

Jason Sutich

Ground delay at SEA Airport after thunderstorms hit the region

A ground delay has been issued for flights arriving at Seattle-Tacoma International Airport after thunderstorms swept through the region Thursday.

7 days ago

Drivers use the High Occupancy Vehicle (HOV) lane, also called the diamond or commuter lane. (Photo...

Chris Sullivan

When is a left lane camper not really camping?

Is there anything worse than a left lane camper? It's time for a reminder on what is and isn't the congestion-causing behavior that drives us nuts.

7 days ago

revive I-5 tolls I-405 commute...

Chris Sullivan

90-minute morning commutes return as Revive I-5 swings back into action

As expected, the drives out of Snohomish County were awful, some of the worst travel times we've seen since the project started again in January.

8 days ago

SR 99 tunnel is built. Why can’t we use it yet?