Weekend construction closures push into Monday morning, causing big delays

May 11, 2026, 6:00 AM | Updated: 7:19 am

1st avenue s bridge closures...

Two NB lanes of SR 99 First Avenue Bridge in Seattle closed following "routine inspection." (Photo courtesy of KIRO 7)

(Photo courtesy of KIRO 7)

Not finishing on time — it’s a risk construction workers face on any job,

The Washington Department of Transportation (WSDOT) had several construction projects run over their anticipated timelines, pushing weekend closures into the Monday morning commute.

I-405

The biggest is on I-405 at 85th Street in Kirkland. That interchange was closed all weekend, including all freeway on- and off-ramps. Workers encountered a groundwater issue during weekend work, delaying their progress.  The entire interchange remains closed and will be until later Monday. The northbound off-ramp from I-405 to 85th Street will remain closed until late this afternoon.

SR 99 First Avenue South Bridge

The northbound lanes of the SR 99 First Avenue South Bridge were also scheduled to reopen to traffic early this morning, but an unexpected mechanical issue prevented them from reopening on time. As of 6 a.m. Monday, SR 99 First Avenue South Bridge reopened after an hour delay.

Chris Sullivan is a traffic reporter for KIRO Newsradio. Read more of his stories here. Follow KIRO Newsradio traffic on X.

Please follow our Community Guidelines

Chokepoints

copper wire theft lighting lakewood...

Chris Sullivan

Wire theft knocks out more lighting along I-5 in Lakewood

Here we go again. Thieves who ripped wire from Washington State Department of Transportation electrical boxes impacted drivers in Lakewood earlier this week.

3 hours ago

othello crash sr 24...

MyNorthwest Staff

11 injured in work bus, semi-truck crash on SR 24 near Othello

At least 11 people were injured in a "critical incident" after a work bus and semi-truck collision on SR 24 near Othello Thursday morning.

6 hours ago

wa toll...

Chris Sullivan

Get ready, drivers: Puyallup to Lynnwood could cost $54 in tolls

We're less than a year from the expansion of the express toll lane system between Renton and Bellevue, marking the start of segmented tolling.

8 hours ago

revive I-5 tolls I-405 commute...

Nate Connors

Revive I-5 on Ship Canal Bridge to end 2 months ahead of schedule

WSDOT announced it has moved up Revive I-5's completion date to the weekend of Oct. 30, which is two months ahead of schedule.

19 hours ago

train puyallup...

MyNorthwest Staff

Man in wheelchair killed after being hit by train in downtown Puyallup

Two people have been hit by a train in downtown Puyallup.

20 hours ago

Snoqualmie Pass Closure...

MyNorthwest Staff

Westbound I-90 back open at Snoqualmie Pass after winter preparation

Westbound I-90 has reopened after a temporary closure at Snoqualmie Pass.

1 day ago

Weekend construction closures push into Monday morning, causing big delays