New issue may impact opening of Sound Transit’s Eastside light rail line

Sep 21, 2023, 5:11 AM | Updated: 5:21 am

Construction on the Interstate 90 bridge light rail...

Construction on the Interstate 90 bridge (Photo courtesy of Sound Transit)

(Photo courtesy of Sound Transit)

A new problem is threatening to impact the opening date of Sound Transit’s Eastside starter light rail line.

Crews discovered loose and broken tiles on the South Bellevue station passenger platform, according to spokesperson Rachelle Cunningham. “The tiles had some issues. The biggest of which is that the tiles (that were installed) were intended for inside use, they were way too slippery to use outdoors.”

Cunningham said some of the tiles also cracked in the summer heat.

“They sort of buckled against each other and lifted up,” she said.

Now the race is on to fix it, with tile removal set to begin next week.

“It’s a safety concern, and we need to have it corrected before the two lines open,” Cunningham said. “The concern is particularly high given that the affected area is on a central platform where riders can board either an east- or westbound train, and where any loose or broken tiles could present a tripping hazard.”

This 10,000-square-foot retrofit could cost $3 million, according to a transit staff report issued last Thursday. Sound Transit says blame for the problem lies with the prime contractor, Shimmick-Parsons Joint Venture. Cunningham says there have been several previous disputes over the contract for the $364 million, 2.2-mile South Bellevue segment.

Another contractor has now stepped in to finish the project, and Cunningham says Sound Transit plans to seek compensation from Shimmick-Parsons to reimburse transit taxpayers for the added costs. According to Thursday’s transit report, Shimmick-Parsons “disagrees with Sound Transit’s determination of defective work and refuses to complete the necessary repairs.”

Another setback

This is the latest in a series of setbacks for the $3.8 billion, 14-mile East Link line — stretching from Redmond Technology Station near Microsoft to the International District/Chinatown Station in Seattle. The project was approved by voters in 2008 and scheduled to open this past July but is now delayed until 2025.

Multiple sections have required additional work, most notably the 5,455 flawed concrete track supports, known as plinths, which were discovered in 2022. It required Sound Transit to rip up around 4 miles of track and rebuild the plinths in the former express lanes of I-90.

Recently, the Sound Transit board agreed to an early opening of the eight stations that form a “starter line” east of Lake Washington. It’s estimated to carry around 6,000 passengers daily, with trains running every ten minutes between South Bellevue and Redmond.

Sound Transit says if weather permits, the tile replacement at the South Bellevue station should be installed by January or early February, in time for the planned Spring 2024 opening.

Follow Kate Stone on X, formerly known as Twitter, or email her here.

Please follow our Community Guidelines

KIRO Newsradio

macklemore (1)...

John Curley Show

‘This is all about Macklemore’s bottom line, baby’: Comedian rips rapper’s Palestine speech as a career play

New York-based comedian Eitan Levine had a sharp take on Macklemore's removal from Ed Sheeran's Loop Tour.

60 minutes ago

Oreogate...

Katrina Guischard

‘Oreogate’ has parents picking sides over a kindergartner’s lunchbox

A chocolate sandwich cookie has become the center of a viral parenting showdown, real or not, dubbed "Oreogate."

3 hours ago

costco (3)...

Jake Skorheim and Spike O'Neill Show

‘I got really, really mad’: Jake celebrates as Costco brings back fan-favorite food court item

Costco has officially confirmed it is bringing back churros to its food court, and KIRO host Jake Skorheim said it's about time.

4 hours ago

Spooner Farms...

Gee Scott and Ursula Reutin Show

‘We were blindsided’: Spooner Berry Farms owner says Olympia gave her two weeks to move a 43-year berry stand

After more than four decades selling berries on Yelm Highway in Olympia, Spooner Berry Farms owner Sue Spooner said the city told her to get out.

5 hours ago

Drew Lock...

Gee Scott

Gee: Wait, what?! Drew Lock gets a chance to rewrite his story

Wait, what?! Drew Lock will start at quarterback for the Seahawks on Sunday in Arizona with Sam Darnold out.

6 hours ago

Ocean Shores shark...

John Curley Show

‘The head’s missing, we’ll have no idea’: Curley has questions after decapitated shark washes up near Ocean Shores

A thresher shark washed ashore near Ocean Shores last week.

7 hours ago

New issue may impact opening of Sound Transit’s Eastside light rail line