Demolition of cracking 520 project column to begin soon

Nov 29, 2022, 5:11 AM | Updated: 5:13 am

Ramp support needs to be replaced...

A construction company needs to replace the SR-520 concrete pier cap that resides above I-5 in Seattle, which inspectors found to have cracks and holes during an October inspection. (Courtesy of WSDOT)

(Courtesy of WSDOT)

We found out earlier this month that a concrete column built just this year on the State Route 520 project is already crumbling and needs to be replaced.

The problem was obvious as soon as the wooden forms were removed from the pier in October.  The concrete was breaking off. Re-bar was exposed. And the cracks were large. There was no doubt it would have to be rebuilt.

SR 520 ramp closed through February for vibration testing

“We’ve been working with the contractor on a rebuilding plan to determine the best possible way they can go out there and take that crossbeam down and rebuild it,” the Washington State Department of Transportation’s (WSDOT) Tony Black said.

Black said the column is fine. It’s the top cap that needs to be replaced. A demolition plan should get underway in a few weeks, and the entire rebuild should be done before the end of the year.

“It will likely take a few days, and it will likely be at night,” Black said.

I promised westbound 520 drivers that they would get their second lane to southbound Interstate 5 back early next year. Will this work delay that from happening?

“That lane reduction wasn’t just for the concrete pier,” Black said. “It was mostly for the work zone areas around there.” That lane restriction should be eliminated by the end of February.

The other big question is, who will pay for this mistake? WSDOT said the contractor will eat the cost.

New ‘ramp support’ over I-5 needs to be replaced

Just a reminder of what WSDOT is doing here. This column will help support a new concrete flyover ramp connecting the 520 and the I-5 Express Lanes. It will be a reversible lane that will switch with the express lanes. It will go westbound 520 to southbound I-5 in the morning and northbound I-5 to eastbound 520 in the afternoon.

It is scheduled to open in 2024, about the same time as the Montlake Lid project wraps up.

This reversible lane will begin as a bus-only lane, but it will convert to an HOV lane for all vehicles when the 520 connection to I-5 is complete in about nine years.

Check out more of Chris’ Chokepoints.

Please follow our Community Guidelines

Chokepoints

Sound Transit light rail lake washington...

Jillian Raftery

Sound Transit has a dead fish problem

Thousands of fish have been found dead in Lake Washington, possibly electrocuted by equipment from the new Crosslake light rail system.

3 days ago

Woodinville speed cameras...

Lexi Herda, KIRO 7 News

Speed cameras are up in these Woodinville school zones

Woodinville has added speed cameras near certain school zones to encourage safer driving and protect students.

3 days ago

2 seattle traffic labor day...

Ted Buehner

Seattle is the No. 1 Labor Day destination in the U.S. Here’s what travelers need to know

As the summer season wraps up, AAA reports well over 100 million people are expected to travel during the Labor Day holiday weekend.

3 days ago

Washington State Ferry San Juan Island cancelled...

Nate Connors

Record summer for Washington ferries caps off with 400K expected over Labor Day weekend

It was a banner summer season for ferry passengers, recording 7 million riders between Memorial Day weekend and the end of August.

4 days ago

Bellevue crash...

MyNorthwest Staff

I-405 south in Bellevue cleared following crash

Four lanes are blocked on I-405 south in Bellevue due to a collision.

4 days ago

Light rail Pinehurst Station Sound Transit...

Lexi Herda, KIRO 7 News

Sound Transit announces opening date for Link light rail’s Pinehurst Station

Sound Transit announces opening date for Link light rail’s Pinehurst Station

4 days ago

Demolition of cracking 520 project column to begin soon