Bertha 14 feet from fresh air, improvements to finish project

Feb 18, 2015, 8:09 AM | Updated: 4:33 pm

After 20 feet of concrete is removed from its path, Bertha will be lifted out of the hole its sat i...

After 20 feet of concrete is removed from its path, Bertha will be lifted out of the hole its sat in since July 2013 and receive some improvements to finish its journey. (Photo Courtesy of WSDOT)

(Photo Courtesy of WSDOT)

Bertha dug for the first time in more than a year Tuesday night and has progressed six feet.

The tunneling machine dug three feet Tuesday night, followed by an additional three feet on Wednesday, according to the Washington State Department of Transportation.

Bertha will receive some much-needed upgrades once the tunneling machine is lifted out of the hole it has sat in for months.

About 14 feet of concrete stands between Bertha and fresh air. Once the machine is exposed, workers will begin disassembling it and lifting it to the surface, Seattle Tunnel Partner’s Chris Dixon said.

Seattle tunnel opponents: No gas tax dollars for Bertha

“We have the ability to remove the cutter head and the cutter drive unit as one piece, but in order to lift those out, we’re going to be disassembling the front part of the shield [in three pieces],” said Dixon.

When Bertha is out of its hole, workers will replace the machine’s bearings, seals and add new components to try and keep the world’s largest tunneling machine from overheating. Additional steel plates will be added to the machine’s components to add strength, said Dixon.

According to the latest timeline, tunneling should resume in April. That’s been the working date since last year, but that didn’t factor in the delays workers experienced handling the groundwater in the repair shaft.

Dixon is confident the project will get back on track. “The project’s very, very important, we’re going to complete the project, we’re going to complete it successfully.”

So here are the key facts when considering all of this:

First, we have no idea how far this 14-month delay has cost the project. No one will say exactly how much this has pushed the budget or who will pay for it, though the city and the state are quite certain Seattle Tunnel Partners will be on the hook. But that might be up to a court to decide.

Bertha has made it about 1,000 feet. It still has 8,000 feet to dig before it pops out near Seattle Center.

Under the original timeline, the tunneling would have been finished by now, and the tunnel would have opened to drivers in December.

The latest estimate is that it will be August of 2017 before the tunnel opens.

The good news is that the work on either end of the tunnel continues to go forward, and most of that work has been completed.

That’s why the state said this project is 70 percent complete, even though the 30 percent left is hardest part and represents the biggest undertaking in the entire project.

Below, WSDOT crews cut into the pit wall where Bertha will eventually emerge. The process is similar to scoring a surface before you cut into it, WSDOT reports. The process will allow concrete to break away in a controlled manner.

Please follow our Community Guidelines

MyNorthwest News

Lynnwood jewelry store shots fired...

Frank Lenzi

Suspects ram pickup into Lynnwood jewelry store; employee starts shooting

An employee opened fire during a violent attempted robbery at a Lynnwood jewelry store, where suspects rammed a pickup truck into the business.

1 hour ago

trump los angeles san diego...

Gee Scott

Gee: Wait, what?! Don’t change the standard because Trump’s your guy

Gee Scott challenges political double standards after Trump’s remarks about Los Angeles and San Diego, arguing loyalty shouldn’t mean abandoning accountability.

2 hours ago

sales tax...

KIRO Newsradio staff

King County Council approves sales tax increase without seeking voter approval

The King County Council approved a sales tax increase Tuesday to support children and families.

2 hours ago

mother arrested...

MyNorthwest Staff

Mother arrested in Edmonds in connection with death of 2-year-old child

A mother was arrested Tuesday in Edmonds in connection with the death of her 2-year-old child. The 44-year-old woman was booked on charges of first-degree manslaughter domestic violence, according to the Snohomish County Sheriff’s Office. Her 2-year-old child died in November 2022 in Lynnwood. Deputies responded to reports of an unresponsive child and performed lifesaving […]

2 hours ago

wa post office burglary...

MyNorthwest Staff

‘Tremendously disruptive’: Post office burglary crew targeted 5 WA counties; final defendant gets 18 months

The last of three South Sound region residents was sentenced to federal prison Monday for their involvement in a post office burglary scheme.

3 hours ago

EdmondsKingston...

Nate Connors

Washington State Ferries to suspend Edmonds/Kingston route

The Edmonds/Kingston ferry route will be suspended for railroad work.

4 hours ago

Bertha 14 feet from fresh air, improvements to finish project