Feds wrap up I-5 bridge collapse probe, replacement work speeding up

Jun 5, 2013, 4:20 PM | Updated: 4:37 pm

Federal investigators have wrapped up their probe at the scene of the I-5 Skagit River bridge crash, and work is well underway on a temporary fix.

The National Transportation Safety Board said investigators interviewed the driver of the pilot vehicle escorting the oversized truck over the bridge on Monday.

She was described as “very cooperative,” and said she saw the bridge collapse in her rearview mirror. Her account “did not reveal anything unusual or of significant interest to investigators,” the NTSB said in a statement.

With the NTSB leaving the site, Washington Department of Transportation crews can now complete the underwater demolition of the fallen bridge section and speed work on a temporary replacement.

“It’s like a giant erector set that’s being built and it’s really impressive how fast our crews are moving to get that structure built,” said WSDOT spokesman Bart Treece.

Treece said work remains on schedule to get the temporary bridge opened by mid-June.

The NTSB and State Patrol continues searching for the driver of a second tractor-trailer who crossed the bridge at the same time as the oversized load that caused the collapse.

Please follow our Community Guidelines

MyNorthwest News

Starbucks (3)...

MyNorthwest Staff

Starbucks shutters another Seattle store as closures and layoffs mount

Starbucks has closed another store in Seattle, this time downtown.

16 minutes ago

seattle traffic...

Nate Connors

Major sports events, full closure on I-405 will make for very busy Seattle commute all weekend

This weekend around the Seattle area might go down as one of the busiest of the summer for the Washington State Department of Transportation.

2 hours ago

Andre Sayles (2)...

James Lynch

‘My feet are here’: Interim SPD Chief Andre Sayles addresses crime, Mayor Katie Wilson, and Seattle’s path forward

Interim Seattle Police Chief Andre Sayles said he’s committed to Seattle and focused on restoring trust and safety.

2 hours ago

Burien Power outage...

MyNorthwest Staff

More than 2,200 without power in Burien

More than 2,200 customers are without power in Burien.

3 hours ago

jimothy night (1)...

MyNorthwest Staff

Raccoon crashes Seattle Mariners’ first Jimothy Night — event returns tonight

The Seattle Mariners celebrated "Hot Jimothy Summer" with a special night honoring viral raccoon Jimothy on Wednesday.

4 hours ago

Salesforce...

Julia Dallas

Salesforce to lay off 59 employees in Seattle and Bellevue

Salesforce, a major customer relationship management platform, is laying off 59 workers in Seattle and Bellevue.

5 hours ago

Feds wrap up I-5 bridge collapse probe, replacement work speeding up