Seattle Tunnel Contractor seeks $125 million from WSDOT for Bertha repairs

Apr 22, 2014, 2:05 PM | Updated: Apr 23, 2014, 7:45 am

The head of the Seattle tunnel project says getting Bertha moving again could cost around $125 million. And the contractor wants the state to pay for it.

The Washington State Department of Transportation confirmed Tuesday that Seattle Tunnel Partners requested $125 million from WSDOT to pay for repairing the Highway 99 tunneling machine. But in a statement, WSDOT officials say the agency has denied STP’s request.

“WSDOT and STP will use processes laid out in the contract to determine the next steps and who is responsible for costs associated with the stoppage. We have seen no evidence that suggests WSDOT or taxpayers will be responsible for costs associated with the current delay,” the statement said.

The Seattle Times reports Chris Dixon, project director for Seattle Tunnel Partners (STP), mentioned the figure to repair and restart the Highway 99 tunneling machine during a briefing Tuesday with the newspaper’s Editorial Board. He said it wasn’t a hard number.

STP announced Monday Bertha would not resume drilling again until next March. Dixon’s comments Tuesday were the first time officials with the project have associated a specific cost with the ongoing delays since Bertha ground to halt because of mechanical problems in December.

The big question is who will actually pay the cost for the repairs and delays. STP blames WSDOT, arguing a steel pipe left by state engineers during groundwater tests caused the damage to the world’s largest drilling machine. But state officials have argued the pipe was documented and STP should have known about its location and avoided drilling into it.

Dixon was joined at the briefing by Todd Trepanier, WSDOT’s Highway 99 program administrator. The pair reportedly emphasized they have maintained a close professional relationship despite the rift between the contractor and the state and ongoing disputes.

Dixon said Monday STP plans to start building a 125-foot deep circular pit next month in front of Bertha that will allow crews to remove the machine’s cutterhead and begin repairing damage to the seal system and main bearing.

Please follow our Community Guidelines

MyNorthwest News

pierce transit (1)...

Nate Connors

Chill out during this week’s heat wave courtesy of Pierce Transit

It's become a regular service to Pierce County residents during the excessive heat bursts we often get throughout our summer season.

1 hour ago

Gifford Pinchot National Forest (1)...

Julia Dallas

Gifford Pinchot National Forest issues emergency closures for wildfire

The Gifford Pinchot National Forest has issued an emergency closure order for the High Lava Fire.

2 hours ago

washington...

James Lynch

Crime drops across every major category in Washington, but officials warn the full picture is more complicated

Crime declined across every major category in Washington in 2025, with sharp drops in murders, violent crime, and property crime.

2 hours ago

seattle homelessness...

Frank Lenzi

Seattle, King County plan to reclaim nearly $160M in homelessness contracts from KCRHA

The King County Regional Homelessness Authority (KCRHA) will survive despite calls from some Seattle and King County leaders to dissolve it.

3 hours ago

King County Metro...

KIRO 7 News Staff

King County Metro to add 9 new bus routes and 3,000 additional weekly bus trips to schedule

King County Metro is adding nine new bus routes and more than 3,000 additional weekly bus trips to its schedule.

3 hours ago

Blue Angels Seattle cancel...

Gee Scott and Ursula Reutin Show

‘It was the right thing to do’: Seafair meteorologist defends decision to cancel the Blue Angels’ Saturday show

Seafair's Blue Angels show canceled due to high winds. Meteorologist explains the decision behind prioritizing safety in Seattle.

4 hours ago

Seattle Tunnel Contractor seeks $125 million from WSDOT for Bertha repairs