CHOKEPOINTS

Will weather finally allow for closure of westbound Highway 2?

Jul 16, 2019, 5:56 AM | Updated: 10:30 am

Highway 2...

Workers jackhammering around expansion joint along US 2 last summer. (WSDOT, Flickr)

(WSDOT, Flickr)

If at first you don’t succeed, try, try again. The state hoped for better weather this weekend to finally get back to work on the Highway 2 trestle between Snohomish and Everett. But here we go again.

Telling the US 2 trestle tolling truth

Weather has once again postponed the road work, this time until Aug. 2.

You’ve probably heard me warn you about upcoming lane closures on the trestle since late spring of 2018. Last year, the project was postponed and postponed again, time after time, because the weather conditions just never cooperated.

It took until mid-summer before the state was able to get to work, and the contractor was only able to get four of the six weekend closures in before the weather turned again.

Fast-forward to this year, and history is repeating itself. The work to repair the westbound lanes of the trestle has been postponed three times already. This latest move is the fourth.

“We need completely dry conditions and warmer overnight temperatures,” says WSDOT’s Frances Fedoriska.

This work needs very specific conditions because the westbound trestle is covered in asphalt. To top it off and lay down the new layer, the state would like to have daytime temperatures in the 80s and overnight lows above 60 and no rain; not even drizzle.

“Any rain impairs our ability to lay down that waterproof coating that we need to protect the structure,” she said. The eastbound trestle is concrete, which doesn’t require such perfect conditions.

Fedoriska said the contractor has some time to play with this summer, so the state isn’t too worried about completing the work.

Northwest set for reprieve as wetter, light wildfire season approaches

“We need up to two more closures, whereas last year we were hoping to get in all six,” she said. “The contractors are going to wait for the perfect conditions to get the work done and get it done right.”

Should the work happen, Fedoriska said all westbound access across the trestle will be blocked.

Highway 2 preparing for a very busy construction season

“This is a full westbound closure between State Route 9 and I-5,” she said.

This is expected to cause major problems across Snohomish County, as most of the drivers who would normally use the trestle will be forced onto Highway 9, which can’t handle a lot of extra traffic on weekends. They are expected to divert into Marysville and Mill Creek to get around the closure.

So, will it happen?

It’s going to be close. The weekend forecast is dry, but the expected daytime temps and overnight lows a few degrees below the optimal conditions.

I’ll keep you posted.

Chokepoints

ritzville i-90 closed visibility...

Jason Sutich

I-90 in Ritzville reopens after dust storm caused multiple collisions

I-90 in Ritzville has reopened after both directions were blocked Friday due to multiple collisions.

1 day ago

super load marysville...

Chris Sullivan

Super load stuck on I-5 south in Marysville should move tonight

A truck carrying a massive pre-fab building has been parked along the southbound I-5 ramp at 88th St. in Marysville for three days.

2 days ago

closure (1)...

MyNorthwest Staff

I-5 reopens in both directions between Maytown and Tumwater

I-5 has reopened in both directions in Thurston County at milepost 97, KIRO Newsradio confirmed.

2 days ago

oyster run anacortes...

Nate Connors

43rd annual Oyster Run returns this weekend in Anacortes

The Oyster Run welcomes thousands of motorcyclists to Skagit County by Figaldo Bay. It's loud, it's proud, and it takes over Anacortes this time each year.

2 days ago

sounder train shoreline...

MyNorthwest Staff

All S Line trains stopped after woman hit in SODO

All Sound Transit S Line trains have been stopped after a woman was hit in SODO Thursday.

2 days ago

Pinehurst Station light rail...

Chris Sullivan

Sound Transit to open new light rail station 5 years ahead of schedule

Sound Transit isn't known for being on time or on budget with its light rail projects, but it's about to open a new station way ahead of schedule.

3 days ago

Will weather finally allow for closure of westbound Highway 2?